St Lawrence Street and Durham Street Reconstruction Schedule Update: Thursday, September 25th,2025

Schedule Update:
September 25–26, 2025
-
Deficiency cleanup throughout St. Lawrence Street and Durham Street
-
Preparing streets for surface asphalt paving
Monday, September 29, 2025
-
Downtown detours in effect for:
-
Asphalt milling (butt-joints)
-
Street sweeping
-
-
Roads will reopen upon completion of this work
Tuesday, September 30, 2025
-
Surface asphalt paving on:
-
Durham Street (North & South)
-
St. Lawrence Street West (Russell)
-
St. Lawrence Street East (Davidson)
-
-
Detours in effect in all paving areas
-
Line painting will follow immediately after paving
Wednesday, October 1, 2025
-
Downtown reopens to all traffic
-
Detours in effect for:
-
St. Lawrence Street East (Russell to East Limit)
-
Surface asphalt paving continues (anticipated completion by October 3rd)
-
Additional Work
-
Sidewalk construction planned for Russell Street, beginning Monday, September 29th