St Lawrence & Durham Construction Weekly Schedule Update - Sept 22nd to Sept 26th,2025

St Lawrence & Durham Construction Weekly Schedule Update  - Sept 22nd to Sept 26th,2025

Weekly Construction Update

Dates: Monday – Friday
Location: Village of Madoc

General Work

  • Sidewalk / Curb Prep: Ongoing additional preparation throughout town.

  • Deficiency Work: Corrections and deficiency repairs on St. Lawrence Street and Durham Street.

Curbside Work

  • Tuesday:

    • Concrete curb and sidewalk pours will commence at various locations across town.

Important Notes

  • Surface Asphalt Paving:

    • GIP Paving is scheduled to begin surface asphalt paving on Durham Street and St. Lawrence Street starting Monday, September 30 (weather permitting).

  • Resident & Business Notices:

    • CDS will begin delivering notices to affected businesses and residents starting Monday.